Question: Activity Table: The PERT estimation procedure uses pessimistic, most likely, and optimistic estimates of the activity time to obtain the expected value and the standard

Activity Table: The PERT estimation procedure uses pessimistic, most likely, and optimistic estimates of the activity time to obtain the expected value and the standard deviation for each activity. The standard deviation is required only if the analyst wishes to make probability statements about completing the project by a certain date. Using the inputs listed above: 1. Create the network diagram using the PERT method to calculate the estimated duration for each activity; ( 8 marks) 2. Calculate the critical path; (4 marks) 3. Calculate the minimum expected time in which the project can be completed; (5 marks) 4. Show slack values for each activity, together with the latest expected time that any activity can start (or finish) without delaying the project; and ( 8 marks) Total 25 marks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
