Question: ACTIVITY TIME 1 A 2 B 3 C 8 D 6 E 9 F 7 G 1 H 10 I 12 J 2 K 1
|
| |
| ACTIVITY | TIME |
|
| 1 |
| A | 2 |
| B | 3 |
| C | 8 |
| D | 6 |
| E | 9 |
| F | 7 |
| G | 1 |
| H | 10 |
| I | 12 |
| J | 2 |
| K | 1 |
Draw the network diagram of the project (with timing).
Determine the critical path.
Determine the (EF, ES) and (LS, LF) And slack.
Determining the expected time for completion of the EACH PROJECT project.
The probability that the project will be completed within 20 weeks.