Question: Activity Time in Days A 1 B 3 C 4 D 5 E 2 F 1 G 2 If activity D decreases to 1 day

| Activity | Time in Days |
| A | 1 |
| B | 3 |
| C | 4 |
| D | 5 |
| E | 2 |
| F | 1 |
| G | 2 |
If activity D decreases to 1 day and activity E also decreases to 1 day from the baseline project in Q1, re-calculate and state the new critical path and the new completion time if they change, and location and length of the new slack times by pathway.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
