Question: Activity Time Predecessor A 2 - B 3 - C 5 A D 4 B E 7 C , D F 2 D G 9

Activity
Time
Predecessor
A
2
-
B
3
-
C
5
A
D
4
B
E
7
C,D
F
2
D
G
9
C
H
6
G,E
I
5
E,F
J
7
H,I
Given the information in Question 4 above, what is the slack on activity C?
Correct!
0
2
14
19
28