Question: Activity Time Predecessor A 8 B 4 A C 5 B, F D 12 A 8 D 0 0 4. D 9 E, F L

Activity Time Predecessor A 8 B 4 A C 5 B, F D 12
Activity Time Predecessor A 8 B 4 A C 5 B, F D 12
Activity Time Predecessor A 8 B 4 A C 5 B, F D 12 A 8 D 0 0 4. D 9 E, F L 9 - I 6 C, G 5 1 Question 7 The slack days for the activity Fare O 8 days O 4 days O 37 days O O days 10 days D Question 8 What is the critical path of the project? A-D-E-G-L-H A-B-C-G-1 A-F-C-L-H O A-B-C-I-H