Question: Given the information in the following table: Activity Duration Predecessor A 8 - B 7 A C 8 B D 5 C , B E

Given the information in the following table: Activity Duration Predecessor A 8 - B 7 A C 8 B D 5 C , B E 4 A, B F 6 B, D G 7 C , F H 6 F, G I 5 E, H Calculate the Early Start (ES) of activity I How long will it take to complete the project? Calculate the slack (S) of activity B Calculate the Late Start (LS) of activity F Calculate the Late Finish (LF) of activity B Calculate the Early Finish (EF) of activity G Choose... Choose... Choose... Choose... Choose... Choose... 4 4} 4 4} 4} 4}