Question: Activity TIME(DAYS) Predecessors A 5 none B 8 none C 15 A,B D 12 A,B E 26 C,D F 33 C,D G 8 B,F H
| Activity | TIME(DAYS) | Predecessors | |||
| A | 5 | none | |||
| B | 8 | none | |||
| C | 15 | A,B | |||
| D | 12 | A,B | |||
| E | 26 | C,D | |||
| F | 33 | C,D | |||
| G | 8 | B,F | |||
| H | 6 | E,F | |||
| I | 28 | G | |||
| J | 15 | G,H | |||
| K | 13 | G,H | |||
| What is your estimate of completion times for this project? | |||||
| What is the earliest start time for Activity F? | |||||
| What is the critical Path? | |||||
| What is the slack for activity B? | |||||