Question: PROBLEM THREE (40 points) Given: The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities,

PROBLEM THREE (40 points) Given: The table shownPROBLEM THREE (40 points) Given: The table shown

PROBLEM THREE (40 points) Given: The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities, and the network diagram for said project. All durations are in days, and all costs are in dollars. The network diagram for the project is also shown below. Activity Immediate Normal Normal Crash Crash Predecessor Duration Cost Duration Cost A 6 100 4 500 10 200 10 200 A 3 50 2 300 B, C 4 150 4 150 E 4 250 3 450 7 200 7 200 G E 2 1 100 - NY 50 5 G A A E B D 2 F 3 4 Required: Determine a) The critical path; b) The normal duration and the normal cost of the project, and c) By how many days can this project be crashed, and at what cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!