Question: Activity Total PV 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1 6 6 2 20 10 10 3
| Activity | Total PV | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | 6 |
| 6 |
|
|
|
|
|
|
|
|
|
|
|
|
| 2 | 20 |
|
| 10 |
| 10 |
|
|
|
|
|
|
|
|
|
| 3 | 30 |
|
| 9 | 6 | 6 | 6 | 3 |
|
|
|
|
|
|
|
| 4 | 20 |
|
| 8 | 2 | 5 | 5 |
|
|
|
|
|
|
|
|
| 5 | 16 |
|
|
|
|
|
|
| 4 | 4 | 4 | 4 |
|
|
|
| 6 | 18 |
|
|
|
|
|
| 9 | 9 |
|
|
|
|
|
|
| 7 | 8 |
|
|
|
|
|
|
|
|
|
|
| 4 |
| 4 |
Status Report: Ending Period 5
| Task | % Complete | EV | AC | PV | CV | SV |
| 1 | Finished |
| 5 |
|
|
|
| 2 | 50% |
| 8 |
|
|
|
| 3 | 60% |
| 12 |
|
|
|
| 4 | 70% |
| 10 |
|
|
|
| Cumulative Totals |
|
|
|
|
| |
Filling the table (4 points)
Determine CPI (1 points), ETC (1), and EAC (1 point each)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
