Question: Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4
Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8.
| Time Period | ||||||||||||||||||||||
| Task | DUR | ES | LF | SL | Budget (PV) | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | ||
| A | 2 | 0 | 2 | 0 | 420 | 200 | 220 | |||||||||||||||
| B | 6 | 2 | 8 | 0 | 2500 | 200 | 700 | 200 | 600 | 200 | 600 | |||||||||||
| C | 5 | 2 | 9 | 2 | 1490 | 200 | 400 | 500 | 90 | 300 | ||||||||||||
| D | 4 | 8 | 12 | 0 | 1560 | 360 | 400 | 400 | 400 | |||||||||||||
| E | 3 | 7 | 12 | 2 | 1000 | 400 | 400 | 200 | ||||||||||||||
| F | 3 | 12 | 15 | 0 | 610 | 200 | 110 | 300 | ||||||||||||||
| Period PV total | 200 | 220 | 400 | 1,100 | 700 | 690 | 500 | 1,000 | 760 | 600 | 400 | 400 | 200 | 110 | 300 | |||||||
| Cumulative PV total | 200 | 420 | 820 | 1,920 | 2,620 | 3,310 | 3,810 | 4,810 | 5,570 | 6,170 | 6,570 | 6,970 | 7,170 | 7,280 | 7,580 | |||||||
(Do not round intermediate calculations. Round your table answer entries to the nearest whole number.)
|
|