Question: Activity Y cannot start until five days after the start of Activity X is an example of a relationship. Start to Start Start to Start
Activity Y cannot start until five days after the start of Activity X is an example of a relationship.
Start to Start
Start to Start with a Lag
Start to Finish with a Lag
Finish to Start
Finish to Finish