Question: Question 6 1 pts Activity Y cannot start until five days after the finish of Activity X is an example.of a _ relationship. Finish to

 Question 6 1 pts Activity Y cannot start until five days

Question 6 1 pts Activity Y cannot start until five days after the finish of Activity X is an example.of a _ relationship. Finish to Start withs Lay Start to Finish within ten Start to start Firsh to Start Finish to Finish