Question: ActivityNormal Time ( weeks ) Crash Time ( weeks ) Normal CostCrash CostImmediate Predecessor ( s ) A 4 3 $ 2 , 0 0
ActivityNormal Time weeksCrash Time weeksNormal CostCrash CostImmediate PredecessorsA$$B$$C$$D$$A BE$$CF$$D EG$$E Fa What is the critical path b What is the project length? c If you wish to reduce the time required to complete this project by week, which activity should be crashed, and how much will this increase the total cost? d If you wish to take another week off the project, which activity would you choose and what is the total cumulative cost? e What is the maximum time that can be crashed? How much would costs increase? $