Question: For the following Project: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Crash Cost Immediate Predecessor A 4 3 $2,000 $2,100 - B 2

For the following Project:

Activity

Normal Time (weeks)

Crash Time

(weeks)

Normal Cost

Crash Cost

Immediate Predecessor

A

4

3

$2,000

$2,100

-

B

2

1

$2,200

$2,800

-

C

3

3

$500

$500

-

D

8

6

$2,300

$2,600

A

E

6

3

$900

$1,200

B

F

3

2

$3,000

$4,200

C

G

4

2

$1,400

$2,000

E, F

How long will the project take?

12 weeks

10 weeks

9 weeks

8 weeks