Actual hours worked: 200 Standard hours: 250 Actual rate per hour: $12 Standard rate per hour: $10
Fantastic news! We've Found the answer you've been seeking!
Question:
Actual hours worked: 200 Standard hours: 250 Actual rate per hour: $12 Standard rate per hour: $10
Given the information above, which of the following is correct regarding direct manufacturing labor variances?
a. The price and efficiency variances are favorable.
b. The price and efficiency variances are unfavorable.
c. The price variance is favorable, while the efficiency variance is unfavorable.
d. The price variance is unfavorable, while the efficiency variance is favorable