Question: Add the Work package durations and complete the calculations to determine the ES (early start), EF (early finish), LS (late start), LF (late finish), and

Add the Work package durations and complete the calculations to determine the ES (early start), EF (early finish), LS (late start), LF (late finish), and Slack in each work package box, as well as the total project duration and clearly identify the critical path

Work package Duration (days) Predecessors 1.1 Demolition: remove all old appliances, cabinets, and flooring 3 None 1.2 Demolition: haul away all materials/debris 1 1.1 2.1 Order cabinets 2 1.2 2.2 Order sink/faucet 1 1.2 2.3 Order appliances 1 1.2 2.4 Order paint 2 1.2 3.1 Create countertop subcontract 1 2.1 & 2.2 & 2.3 3.2 Create tile subcontract 3 2.1 3.3 Create painting subcontract 1 2.4 4.1 Install cabinets 3 3.1 4.2 Install countertop 1 3.2 & 4.1 4.3 Install tile floors 4 4.2 4.4 Install sink/faucet 1 4.3 4.5 Install appliances 2 3.3 & 4.4 5.1 Paint walls & ceiling 4 4.5 6.1 PM Inspection/punchlist 1 5.1 6.2 Walk through / acceptance 1 6.1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!