Question: Adding resources to reduce the amount of time it takes to complete project activities is called: Select one: a . crashing b . scope creep
Adding resources to reduce the amount of time it takes to complete project activities
is called:
Select one:
a crashing
b scope creep
c simulation
d indirect project costs