Question: Additional Algo 1 9 - 1 Early Start Time The network diagram and task times for a project are shown below. The process is as

Additional Algo 19-1 Early Start Time
The network diagram and task times for a project are shown below.
The process is as follows:A 1 to A 2 and A 3. A 2 and A 3 to A 4 then A 5.
Task Duration (days)
A1
7
A2
1
A3
4
A4
4
A5
7
What is the early start time for activity A5
?