Question: The network diagram and task times for a project are shown below. The process is as follows:A 1 to A 2 and A 3 .

The network diagram and task times for a project are shown below.
The process is as follows:A 1 to A 2 and A 3. A 2 and A 3 to A 4 then A 5.
Task Duration (days)
A1
9
A2
8
A3
5
A4
3
A5
3
What is the early start time for activity A5
?