Question: Additional Algo 4-7 Line Balancing A process includes 9 tasks and there are 3 workers, Each task can be assigned to only one worker and
Additional Algo 4-7 Line Balancing A process includes 9 tasks and there are 3 workers, Each task can be assigned to only one worker and each worker must be assigned consecutive tasks. The time to complete tasks 1 to 9 (in seconds) are as follows: 90,75,25,25,50,30,10,80,90 What is the capacity of this process in units per hour? Note: Round your answer to 1 decimal place