Question: Need help Additional Algo 4-7 Line Balancing A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one
Additional Algo 4-7 Line Balancing A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned consecutive tasks. The time to complete tasks 1 to 9 (in seconds) are as follows: 100,45,50,30,25,45,30,70,65 What is the capacity of this process in units per hour? Note: Round your answer to 1 decimel place
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts