Question: Additional Problem 1 7 - 1 ( Algo ) A city hall plans on holding a townhall event at the end of the Fall. The
Additional Problem Algo
A city hall plans on holding a townhall event at the end of the Fall. The activities that have to be completed, duration of each activity, and their sequence are listed in the table below:
Activity Duration weeks Immediate Predecessor
A
B A
C A
D B
E DC
F E
a Determine the project duration.
b What is the earliest start, earliest finish time, latest start, latest finish time for activity E
c What is the slack for activity C