Question: Additional Problem 1 7 - 1 ( Algo ) A city hall plans on holding a townhall event at the end of the Fall. The

Additional Problem 17-1(Algo)
A city hall plans on holding a townhall event at the end of the Fall. The activities that have to be completed, duration of each activity, and their sequence are listed in the table below:
Activity Duration (weeks) Immediate Predecessor
A 2--
B 3 A
C 3 A
D 1 B
E 4 D,C
F 1 E
a. Determine the project duration.
b. What is the earliest start, earliest finish time, latest start, latest finish time for activity E?
c. What is the slack for activity C?