Question: Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U,V - - - U W 35 50 65

Consider the following work breakdown structure:

Duration Estimates (Days)
Activity Precedes Optimistic Most Likely Pessimistic
Start U,V - - -
U W 35 50 65
V W,X 28 40 52
W Z 26 35 44
X Y 28 40 52
Y Z 26 29 38
Z End 36 60 84

What is the probability that the critical path for this project will be completed within 200 days?

Multiple Choice

  • .8413

  • .9772

  • .9987

  • .9544

  • .9974

A city hall plans on holding a townhall event at the end of the Fall. The activities that have to be completed, duration of each activity, and their sequence are listed in the table below:

Activity Duration (weeks) Immediate Predecessor
A 2 --
B 3 A
C 3 A
D 1 B
E 4 D,C
F 1 E

a. Determine the project duration.

b. What is the earliest start, earliest finish time, latest start, latest finish time for activity E?

c. What is the slack for activity C?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!