Question: Additional Problem 1 7 - 1 ( Algo ) A city hall plans on holding a townhall event at the end of the Fall. The

Additional Problem 17-1(Algo)
A city hall plans on holding a townhall event at the end of the Fall. The activities that have to be completed, duration of each activity, and their sequence are listed in the table below:
\table[[Activity,\table[[Duration],[(weeks)]],\table[[Immediate],[Predecessor]]],[A,2,--],[B,3,A],[C,3,A],[D,1,B],[E,4,D, C],[F,1,E]]
a. Determine the project duration.
The longest path is ABDEF= weeks
b. What is the earliest start, earliest finish time, latest start, latest finish time for activity E?
 Additional Problem 17-1(Algo) A city hall plans on holding a townhall