Question: Additional Problem 17-2 (Algo) The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a semester project. C,8 E,3

Additional Problem 17-2 (Algo) The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a semester project. C,8 E,3 es D,4 F,5 a. Determine the earliest start time for activity F. Earliest start time b. If the latest time activities E and Fare to be finished is 13, determine the latest finish time for activity C