Question: Additionally, please perform the following tasks using the tabulated project data shown below. Activity Predecessor Resources Duration A - 1 6 B - 3 5
Additionally, please perform the following tasks using the tabulated project data shown below. Activity Predecessor Resources Duration A - 1 6 B - 3 5 C - 4 4 D A, B 2 4 E A, B, C 3 5 F B, C 2 5 G E, F 1 2 H D, E 3 7 3. Assume resource-constrained conditions (maximum of 5 resource units are available) and minimize the delay in the project. Use the minimum slack heuristic to develop a resource schedule; use the smallest duration and then lowest activity ID for ties. a. Show the "bookkeeping" table presented in the class slides to develop the resource schedule. b. Which activities are now considered critical? c. What are the slack times for each of the non-critical activities
Step by Step Solution