Question: Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by Single choice. (1 Point)
Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by
Single choice.
(1 Point)
Imposed project deadlines
Time to market
Unforeseen project delays
High overhead
2.
Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by
Single choice.
(1 Point)
Imposed project deadlines
Time to market
Unforeseen project delays
High overhead
3.
Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by
Single choice.
(1 Point)
Imposed project deadlines
Time to market
Unforeseen project delays
High overhead
4.
Which of the following is NOT a rational reason to reduce project duration?
Single choice.
(1 Point)
Incentive contracts
High network sensitivity
Imposed deadlines
High overhead costs
5.
Managers have several effective methods for crashing specific project activities when resources are not constrained
Single choice.
(1 Point)
True
False
6.
When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?
Single choice.
(1 Point)
Establishing a core project team
Fast-tracking
Reduce project scope
Compromise quality
7.
When adding resources, there are limits as to how much speed can be gained
Single choice.
(1 Point)
True
False
8.
The shortest possible time an activity can be completed realistically is called ________ time.
Single choice.
(1 Point)
Expedited
Accelerated
Crash
9.
Shortening an activity's duration is termed crashing
Single choice.
(1 Point)
True
False
10.
Which of the following is NOT a technique for accelerating project completion when resources are not constrained?
Single choice.
(1 Point)
Assign additional staff and equipment
Establish a core team
Do it twice-first fast and then correctly
Compromise quality