Question: afinish to start lag delay is shown: a. As a subtracted value in the follower's early finish time. b. As an addition of time to

afinish to start lag delay is shown:
a.
As a subtracted value in the follower's early finish time.
b.
As an addition of time to the predecessor's duration.
c.
Should be shown on the line joining the two sequential nodes .
d.
As an added value in the predecessors early start time.