Question: a)For the job scheduling problem consider the following algorithm: Repeat until no more jobs left: Let J be the job that overlaps with the fewest
a)For the job scheduling problem consider the following algorithm:
Repeat until no more jobs left:
Let J be the job that overlaps with the fewest jobs.
Choose J and remove all jobs that overlap with J.
Show that the algorithm above is not correct. Hint: Give an example where the algorithm does not select the largest possible set. Explain what the algorithm chooses and then show there is a larger set.