Question: After a project delay, the project manager determines that a change is needed to the product deliverables in order to ensure quality. The project manager
After a project delay, the project manager determines that a change is needed to the product deliverables in order to ensure quality. The project manager takes the following steps:
A formal change request is issued.
The project manager communicates the change to all stakeholders.
The project manager receives feedback that the communications approach did not meet stakeholders' expectations.
What should the project manager do next?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
