Question: After an extensive product analysis using group technology, Leon Bazil has identified a product he believes should be pulled out of his process facility and

After an extensive product analysis using group

After an extensive product analysis using group technology, Leon Bazil has identified a product he believes should be pulled out of his process facility and handled in a work cell. Leon has identified the following operations as necessary for the work cell. The customer expects delivery of 250 units per day, and the work day is 420 minutes. a) The takt time for this = minutes (round your response to two decimal places). b) Following are the operations that are required for manufacturing of the product: Operation Shear Bend Weld Clean Paint Standard Time (min) 1.1 1.1 1.7 3.1 1.0 The number of employees requiring to be cross-trained for the new cell = (round your response up to the next whole number). c) Based on the knowledge about the standard times for each of the operations, special consideration may be warranted for the operation

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!