Question: After applying resource leveling to critical path activities you can expect that A. The duration of the critical path will not change B. The duration
- After applying resource leveling to critical path activities you can expect that
A. The duration of the critical path will not change
B. The duration of the critical path will become shorter
C. The duration of the critical path will become longer
D. The critical path will become know as the critical link