Question: Table below presents the activities of a project. Needed Resources (man) Number Activity Duration (day) Pre-Requisite Man/day Cumulative 1. A 4 - 1 4 2.
Table below presents the activities of a project.
Needed Resources (man)
Number Activity Duration (day) Pre-Requisite Man/day Cumulative
1. A 4 - 1 4
2. B 5 A 1 5
3. C 6 A 1 6
4. D 6 C 1 6
5. E 16 A 1 16
6. F 4 E 1 4
7. G 10 E 1 10
8. H 4 F, B, D 1 4
1. Draw the critical path method (AON) and find out the project duration, four times (EST, EFT, LST, and LFT), critical activities and the slack (total float) for each activity. (1)
2. Draw Gantt chart based on the earliest times. (1)
3. Draw the Daily Resources Diagram before smoothing (leveling of resources) and after smoothing (leveling of resources). (1)
4. Draw S curve before and after leveling. (1)
---------------
Please Solve As soon as
Solve quickly I get you thumbs up directly
Thank's
Rawan
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock