Question: After brainstorming potential project risks, what is the recommended method for prioritizing these risks and their mitigation plans? a Fishbone diagram b RACI chart c
After brainstorming potential project risks, what is the recommended method for prioritizing these risks and their mitigation plans?
a
Fishbone diagram
b
RACI chart
c
Probability and impact matrix
d
Control chart