Question: After identifying potential project risks, the project team should then _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
After identifying potential project risks, the project team should then
Group of answer choices
move on to other components of the charter, since identifying risks is the only riskrelated activity in theinitiatingphase
wait for the sponsor to conduct a risk assessment.
develop risk response plans for all identified risks.
assess each risk based on probability and likely impact, and then create a risk response plan for each major risk.