After identifying potential project risks, the project team should then ___________________.
a. develop risk response plans for all identified risks.
b. wait for the sponsor to conduct a risk assessment.
c. move on to other components of the charter, since identifying risks is the only risk-related activity in the initiating phase.
d. assess each risk based on probability and likely impact, and then create a risk response plan for each major risk.