Question: After Ling finished drafting a new project charter, she sent a copy of the charter to all key project parties including the project sponsor, senior

After Ling finished drafting a new project charter, she sent a copy of the charter to all key project parties including the project sponsor, senior management and key stakeholders, and scheduled a kick-off meeting with them. What will be the most important goal for Ling to complete the project charter?
a.
Obtain officially signed project charters from the key parties.
b.
Get confirmation from the key parties that they have read the charter.
c.
Make a professional looking project charter to impress the key project parties.
d.
Gather promises from the key project players.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!