Question: After much consultation, the project manager presented the work breakdown structure for the project. The tasks are listed along with the estimated duration. PROJECT: E-COMMERCE
After much consultation, the project manager presented the work breakdown structure for the project.
The tasks are listed along with the estimated duration.
PROJECT: E-COMMERCE FOR A SMALL SUPERMARKET
Work Breakdown Structure
| Activity Number | Activity | Duration | Activity Predecessor |
| 1 | Gather data | 5 |
|
| 2 | Study Feasibility | 4 |
|
| 3 | Prepare Project Definition Report | 1 | 1,2 |
| 4 | Interview Users | 6 | 3 |
| 5 | Study Existing System | 10 | 3 |
| 6 | Define User Requirements | 6 | 4,5 |
| 7 | Prepare Systems Analysis Report | 1 | 6 |
| 8 | Input & Output | 10 | 7 |
| 9 | Design modelling | 4 | 7 |
| 10 | Processing & Database | 6 | 8 |
| 11 | Prepare Systems Design Report | 2 | 9,10 |
| 12 | Software Development | 20 | 11 |
| 13 | Hardware Development | 5 | 11 |
| 14 | Network Development | 12 | 11 |
| 15 | Hardware Testing | 5 | 13 |
| 16 | Network Testing | 5 | 14 |
| 17 | Software Testing | 10 | 12 |
| 18 | Prepare Testing Report | 3 | 15,16,17 |
| 19 | Training | 5 | 18 |
| 20 | System Conversion | 10 | 18 |
| 21 | Prepare Implementation Report | 6 | 19,20 |
For Activity 13 on the work breakdown structure, various contractors could not agree on the duration. Mr Nxumalos Technology Services estimated 4 days, but Stans Hardware Services said it would take 12 days. The project manager then solicited a third opinion, and Sparks Computing Services suggested that it would take 5 days.
The project manager suggested using the PERT estimation technique to best estimate the duration of activities in line with the approved completion duration of 90 days.
|
| QUESTION 3 NETWORK DIAGRAM
| 25 MARKS |
|
| Required: |
|
| 3.1 | Complete the network diagram of the activities in the sheet provided below, in the correct sequence, dependency and flow.
Use the insert function of Microsoft word or any other suitable application to connect the activities with directional arrows to complete the network diagram.
Complete the forward and back pass in the answer sheet provided. | (25x1 = 25) |
|
|
|
|
| 3.2 | Colour code all tasks on the critical path on the network diagram. | (13) |
|
|
|
|
| 3.3 | Briefly explain the importance of a network diagram in project management to the sponsor | (2) |