Question: After much consultation, the project manager presented the work breakdown structure for the project. The tasks are listed along with the estimated duration. PROJECT: E-COMMERCE

After much consultation, the project manager presented the work breakdown structure for the project.

The tasks are listed along with the estimated duration.

PROJECT: E-COMMERCE FOR A SMALL SUPERMARKET

Work Breakdown Structure

Activity Number

Activity

Duration

Activity Predecessor

1

Gather data

5

2

Study Feasibility

4

3

Prepare Project Definition Report

1

1,2

4

Interview Users

6

3

5

Study Existing System

10

3

6

Define User Requirements

6

4,5

7

Prepare Systems Analysis Report

1

6

8

Input & Output

10

7

9

Design modelling

4

7

10

Processing & Database

6

8

11

Prepare Systems Design Report

2

9,10

12

Software Development

20

11

13

Hardware Development

5

11

14

Network Development

12

11

15

Hardware Testing

5

13

16

Network Testing

5

14

17

Software Testing

10

12

18

Prepare Testing Report

3

15,16,17

19

Training

5

18

20

System Conversion

10

18

21

Prepare Implementation Report

6

19,20

For Activity 13 on the work breakdown structure, various contractors could not agree on the duration. Mr Nxumalos Technology Services estimated 4 days, but Stans Hardware Services said it would take 12 days. The project manager then solicited a third opinion, and Sparks Computing Services suggested that it would take 5 days.

The project manager suggested using the PERT estimation technique to best estimate the duration of activities in line with the approved completion duration of 90 days.

QUESTION 3 NETWORK DIAGRAM

25 MARKS

Required:

3.1

Complete the network diagram of the activities in the sheet provided below, in the correct sequence, dependency and flow.

Use the insert function of Microsoft word or any other suitable application to connect the activities with directional arrows to complete the network diagram.

Complete the forward and back pass in the answer sheet provided.

(25x1 = 25)

3.2

Colour code all tasks on the critical path on the network diagram.

(13)

3.3

Briefly explain the importance of a network diagram in project management to the sponsor

(2)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!