Question: After plotting demand for four periods, an emergency room manager has concluded that a trend-adjusted exponential smoothing 1 to 4 , for an average of

After plotting demand for four periods, an

After plotting demand for four periods, an emergency room manager has concluded that a trend-adjusted exponential smoothing 1 to 4 , for an average of +6.33 units. Click here for the Excel Data File Use =0.50 and =0.10, and TAF of 240 for period 5 . Obtain forecasts for periods 6 through 10 . (Round your intermediate calculations and final answers to 2 decimal places.)