Question: The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with
The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (weeks) as shown in the following table. The project will be finished when activities A-J are all finished.
| Activity | Predecessors | Duration (Weeks) |
| A | 5 | |
| B | 5 | |
| C | A | 11 |
| D | B | 9 |
| E | C | 4 |
| F | C, D | 10 |
| G | E | 4 |
| H | G | 3 |
| I | G | 4 |
| J | F, H | 3 |
- Create an Activity-On-Node network diagram for this Project.
- Calculate the earliest start (ES) and finish (EF) times and latest start (LS) and finish (LF) times, the total slack (TS) and free slack (FS) for each of the activities in the network.
- Identify the critical path(s).
- What is the project completion duration?