Question: The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with

The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (weeks) as shown in the following table. The project will be finished when activities A-J are all finished.

Activity

Predecessors

Duration (Weeks)

A

5

B

5

C

A

11

D

B

9

E

C

4

F

C, D

10

G

E

4

H

G

3

I

G

4

J

F, H

3

  1. Create an Activity-On-Node network diagram for this Project.
  2. Calculate the earliest start (ES) and finish (EF) times and latest start (LS) and finish (LF) times, the total slack (TS) and free slack (FS) for each of the activities in the network.
  3. Identify the critical path(s).
  4. What is the project completion duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!