Question: After potential suppliers have passed the initial evaluation process, the selection process begins, and the project team invites those suppliers to submit bids or proposals.
After potential suppliers have passed the initial evaluation process, the selection process begins, and the project team invites those suppliers to submit bids or proposals. Which of these is NOT one of the evaluation criteria that might be used to rate the supplier proposals?
a. Weighting system
b. Supplier websites
c. Proposal evaluation techniques
d. Independent estimates
If it is agreed that both parties want to share the risk, what type of contract is good to use?
a. Fixed-price contract
b. Wrap-up
c. Cost reimbursable contract
d. Time and material contracts
A number of partnering practices are used in an Agile environment. Which of these is NOT one of the Agile partnering practices?
a. Money for nothing
b. Change for free
c. Graduated fixed price
d. Cost reimbursable
Course: Project Management
Please answer correctly.