Question: After the total slack for each activity is identified, the project manager can more easily identify thea.total project slack.b . earliest start date.c . total
After the total slack for each activity is identified, the project manager can more easily identify thea.total project slack.bearliest start date.ctotal budget.dearned value.ecritical path.