Question: After the total slack for each activity is identified, the project manager can more easily identify the A ) earliest start date. B ) earned
After the total slack for each activity is identified, the project manager can more easily identify the
A earliest start date.
B earned value.
C total budget.
D critical path.
E total project slack.