Question: After using your forecasting model for six months, you decide to test it using MAD and a tracking signal. Here are the forecast and actual
After using your forecasting model for six months, you decide to test it using MAD and a tracking signal. Here are the forecast and actual demands for the six-month period: PERIOD FORECAST ACTUAL May 435 485 June 485 545 July 535 385 August 600 495 September 655 680 October 705 580 a. Find the tracking signal