Question: Ali is an engineer who was recently assigned as a project manager to build a private villa. He has developed the below table. Code Activities

Ali is an engineer who was recently assigned as a project manager to build a private villa. He has developed the below table.

Code

Activities

Duration Days

Predecessors

A

Draw a draft for the villa design

5

No predecessor

B

Obtain the owners approval

3

A

C

Assign the contractor

7

B

D

Assign the interior designer

4

B

E

Finalize the contract

5

D and C

Kindly assist Ali to do the following:

  1. Draw a Network Diagram
  2. Find the Critical Path
  3. Find the Early Start and Early Finish
  4. Find the Late Start and Late finish
  5. Find the float

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!