Question: All activity times for the project are in weeks. Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22
All activity times for the project are in weeks.
| Activity | Predecessor | Optimistic | Most Likely | Pessimistic |
| A | -- | 12 | 16 | 25 |
| B | -- | 7 | 14 | 22 |
| C | -- | 5 | 10 | 14 |
| D | A | 15 | 18 | 25 |
| E | C | 8 | 12 | 18 |
| F | B | 9 | 12 | 15 |
| G | F | 18 | 22 | 29 |
| H | D, E, G | 15 | 19 | 27 |
Using Table 7.13, what is the probability that the project will be completed in 65 or fewer weeks?
Group of answer choices
greater than 24% but less than or equal to 28%
greater than 20% but less than or equal to 24%
less than or equal to 20%
greater than 28%