Question: All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities (A, B, C, and D) that must be performed
All answers were generated using 1,000 trials and native Excel functionality.)
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
Activity Activity Time(weeks) Probability
A 5 0.25
6 0.35
7 0.25
8 0.15
B 3 0.20
5 0.55
7 0.25
C 10 0.10
12 0.25
14 0.40
16 0.20
18 0.05
D 8 0.60
10 0.40
(a)Construct a spreadsheet simulation model to estimate the average length of the project and the standard deviation of the project length. Round your answers to one decimal place.
Average Project Length_______weeks
Standard Deviation in Project Length_____weeks
(b)What is the estimated probability that the project will be completed in 35 weeks or less? Round your answer to a whole percentage.% (THIS IS NOT .65 THAT IS INCORRECT)
(c)BASE CASE SCENARIO
(D) WORST CASE SCENARIO
(E) BEST CASE SCENARIO