Question: (All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities (A, B, C, and D) that must be performed

(All answers were generated using 1,000 trials and native Excel functionality.)

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

Activity Activity Time (weeks) Probability
A 5 0.25
6 0.35
7 0.25
8 0.15
B 3 0.20
5 0.55
7 0.25
C 10 0.10
12 0.25
14 0.40
16 0.20
18 0.05
D 8 0.60
10 0.40

(a) Construct a spreadsheet simulation model to estimate the average length of the project and the standard deviation of the project length.
Round your answers to one decimal place.
Average Project Length weeks
Standard Deviation in Project Length weeks
(b) What is the estimated probability that the project will be completed in 35 weeks or less?
Round your answer to a whole percentage.
%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!