Question: All else constant, the net present value of a project increases when: The initial cost of a project increases. Each cash inflow is delayed by
All else constant, the net present value of a project increases when:
- The initial cost of a project increases.
- Each cash inflow is delayed by one year.
- The discount rate increases.
- The required rate of return decreases.
- All of the above increases the NPV of a project.