Question: All information is showing. The table is the exact same thing that is showing in the excel file. Consider the following information about a small


All information is showing. The table is the exact same thing that is showing in the excel file.
Consider the following information about a small project: Task A B D E F Duration Estimates 2 days 5 days 2 days 4 days 5 days 12 days Immediate Predecessors None A B A B & D E & C pictureClick here for the Excel Data File b-1. Identify the critical path. O A-B-E-F O A-B-C-F O A-D-E-F b-2. Identify earliest start and finish, and slad for each task. (Leave no cells blank - certain ente wherever required.) Task Immediate Predecessors None Earliest Start (ES) Earliest Completion (EC) A B A B D A E BD F CE Task Immediate Successors Latest Completion Latest Start (LS) Slack None E F D E F B C, E B, D c. Which of these activities should the project manager track most closely? A-B-E-F A-D-E-F O A-B-C-FStep by Step Solution
There are 3 Steps involved in it